| Tasks | Sub-Tasks | Teammates | Percentage Completed | Start Date- Due Date | End Date | Time Needed |
| Lab 1 | ~ Received AEV
~ Confirmed materials with AEV checklist |
All | 100% | 1/12/18-1/12/18 | 1/12/18 | 1 hr 20 min |
| Lab 2 | ~ Preliminary Lab 1 (Exercise 1)
~ Preliminary Lab 2 (Exercise 2) |
All | 100% | 1/19/18-2/2/18 | 1/26/18 | 1 hr 20 min |
| Website Update 1 | ~ Create Website
~ Form Links ~ Create Meet the Team ~ Compile Initial Ideas |
All | 100% | 1/12/18-1/19/18 | 1/18/18 | 2 hr |
| Team Meeting Notes | ~ Take Details Notes on What Happens during meetings
~ Compile them together and format accordingly |
Payton | 100% | 1/12/18-1/19/18 | 1/18/18 | 1 hr |
| Lab 3 | ~ Preliminary Lab 3
(Exercise 3) ~ Preliminary Lab 4 (Exercise 4) |
All | 100% | 1/19/18-2/2/18 | 2/2/18 | 1 hr 20 min |
| Website Update 2 | ~ Update Content Regarding Lab Findings
~ Developing Key Areas |
All | 100% | 1/26/18-2/2/18 | 2/1/18 | 2 hr |
| Lab 4 | ~ Preliminary Lab 5
(Exercise 5) |
All | 100% | 2/2/18-2/2/18 | 2/2/18 | 1 hr 20 min |
| Lab 5 | ~ Advanced R&D 1
~ Motor Configuration |
All | 100% | 2/9/18-2/9/18 | 2/9/18 | 1 hr 20 min |
| Progress Report 1 | ~ Write-Up of the Progress Made During Preliminary | All | 100% | 2/2/18-2/9/18 | 2/8/18 | 1 hr 20 min |
| Lab 6 | ~ Committee Meetings
~ Alec and Billy- HR ~ Payton- Public Relations ~ Grant Proposal |
All | 100% | 2/9/18-2/16/18 | 2/16/18 | 1 hr 20 min |
| Lab 7 | ~ Advanced R&D 2
~ Motor Quantity |
All | 100% | 2/23/18-2/23/18 | 2/23/18 | 1 hr 20 min |
| Lab 8 | ~ Oral Presentations | All | 100% | 3/2/18-3/2/18 | 3/2/18 | 1 hr 20 min |
| Website Update 3 | ~ Update Content Regarding Lab Findings
~ Organize Current Findings |
All | 100% | 2/23/18-3/2/18 | 3/1/18 | 2 hr |
| Progress Report 2 | ~ Write-Up of the Progress Made During Preliminary | All | 100% | 3/2/18-3/9/18 | 3/8/18 | 3 hr |
| Final R&D 1 | ~ Rank other Designs
~ Look over Other Divisions Collected Observations ~ Build Final Design |
All | 100% | 3/9/18-3/22/18 | 3/22/18 | 1 hr |
| Performance Test 1 | ~ Create Optimal Code
~ Test Code Before Performance Testing |
All | 100% | 3/9/18-3/22/18 | 3/21/18 | 3 hrs |
| CDR Draft | ~ Executive Summary
~ Results & Discussion ~ Conclusions and Recommendations |
All | 100% | 3/15/18-3/23/18 | 3/23/18 | 6 hrs |
| Final R&D 2 | ~ Check the AEV for any complications
~ Make sure that all objectives are met or are in the process of being met |
All | 100% | 3/23/18-3/29/18 | 3/29/18 | 1 hr |
| Performance Test 2 | ~ Add to Code
~ Test Code Before Performance Testing |
All | 100% | 3/23/18-3/29/18 | 3/27/18 | 3 hrs |
| Committee Meeting 2 | ~ Each member prepare for their roles
~ All documentation will be completed before |
All | 100% | 3/27/18-3/29/18 | 3/29/18 | 1 hr |
| Final R&D 3 | ~ Make sure that energy consumption is optimal
~ Motors utilize energy efficiently |
All | 100% | 3/28/18-4/5/18 | 4/5/18 | 1 hr |
| Progress Report 3 | ~ Compile Data During Performance Tests
~ Discuss Takeaways |
All | 100% | 3/28/18-4/8/18 | 4/8/18 | 3 hrs |
| Final Oral Presentation Draft | ~ Create Powerpoint
~ Compile Data During Performance Tests |
All | 100% | 4/2/18-4/10/18 | 4/9/18 | 6 hrs |
| Final Performance Test | ~ Finalize Code
~ Test Code ~ Change Last Design Flaws |
All | 100% | 3/29/18-4/13/18 | 4/13/18 | 3 hrs |
| Final Oral Presentation | ~ Finalize Powerpoint
~ Practice Presentation |
All | 100% | 4/2/18-4/20/18 | 4/20/18 | 6 hrs |
| CDR | ~ Document All Data Collected
~ Final Thoughts on Project |
All | 100% | 2/23/18-4/20/18 | 4/20/18 | 12 hrs |
| Final Website Update | ~ Compile All Findings
~ Present Final Product |
All | 100% | 3/22/18-4/20/18 | 4/20/18 | 2 hrs |