1/12/18- Lab 1: received AEV and confirmed materials with AEV checklist
1/19/18 – Lab 2: Preliminary Lab 1 and Preliminary Lab2
1/19/18- Team Meeting Notes
1/19/18 – Website Update 1
2/2/18 – Lab 3: Preliminary Lab 3 and Preliminary Lab 4
2/2/18 – Lab 4 and Lab 5
2/2/18 – Website Updates 2
2/7/18- Progress report completion
2/09/18 – Test propeller configuration using data analysis tool.
2/15/18 – Go over next lab’s deliverables
2/16/18 – Test power braking vs. coasting, committee meetings.
2/22/18 – Go over next lab’s deliverables
2/23/18 – Finish power braking tests, continue propeller configuration testing.
2/23/18 – Lab 7 and Lab 8
2/25/18 – Website Update 3
3/2/18 – Prepare for R&D Presentations
3/2/18 – Oral R&D Presentations
3/7/18 – Progress Report 2 Completion
3/9/18 – Complete Performance Test 1
3/23/18 – Complete Performance Test 2
3/30/18 – Committee Meeting 2
4/3/18 – Final Oral Presentation
4/4/18 – Complete Progress Report 3
4/12/18 – Final Performance Test was completed