Meeting 12
Date – 3/1/19
Time – 8:00 am
Location – Hitchcock 224
Members Present – All
Objective – Data for aR&D 1.
Tasks Completed –
Methodologies for Push vs Pull used
Testing for aR&D 1 completed
Tasks to be Completed –
Data needs to be analyzed
Methodologies for aR&D 2 to be updated
Finalize Progress Report
Meeting 13
Date – 3/4/19
Time – 8:00 am
Location – Hitchcock 308
Members Present – All
Objective – Begin planning to Performance Test 1 and aR&D 2
Tasks Completed –
Methodologies updated
Draft code for Performance Test 1 planned out
aR&D 2 completed
Data gathered from aR&D 2
Tasks to be Completed –
Progress Report 2
Performance Test 1
Meeting 14
Date – 3/6/19
Time – 8:00 am
Location – Hitchcock 308
Members Present – All
Objective – Performance Test 1 code
Tasks Completed –
Code written out for Performance Test 1
Progress Report Completed
Tasks to be Completed –
Performance Test 1
Website Update
Testing for Performance Test 1
Meeting 15
Date – 3/8/19
Time – 8:00 am
Location – Hitchcock 224
Members Present – All
Objective – Testing Performance Test 1 code
Tasks Completed –
Tested code for Performance Test 1
Tasks to be Completed –
Work on code for Performance Test 1
Performance Test 1
Website Update
Meeting 16
Date – 3/18/19
Time – 8:00 am
Location – Hitchcock 308
Members Present – All
Objective – Work on Progress Report 2 and Performance Test 1 code
Tasks Completed –
Website Update
Performance Test 1 code
Tasks to be Completed –
Progress Report 2
Performance Test 1
Oral Presentation for aR&D
Meeting 17
Date – 3/19/19
Time – 5:00 pm
Location – Morrison tower lobby
Members Present – All
Objective – Write the second progress report
Tasks Completed –
Nick -Wrote the second half of situation, upcoming goals, and schedule
Dillon – Wrote the first half of situation, takeaways, and created the appendices
Ethan – Wrote the results and analysis and situation for future work
Tasks To Be Completed – Prepare for the oral presentation and the second performance test
Meeting 18
Date – 3/20/19
Time – 8:00 am
Location – Hitchcock 308
Members Present – All
Objective –
Tasks Completed –
Progress Report 2 completed
Performance Test 1 completed
Tasks to be Completed –
Oral Presentation for aR&D
Meeting 19
Date – 3/21/19
Time – 5:30 pm
Location – Morrison tower lobby
Members Present – All
Objective – Finish the aR&D oral presentation
Tasks Completed – aR&D oral presentation draft
Nick – results, methods, and data analysis for push vs pull
Dillon – results and data analysis for battery testing; turn in presentation
Ethan – intro, conclusions, and setup for battery testing
Tasks To Be Completed – CDR draft due lab 14
Meeting 20
Date – 3/22/19
Time – 8:00 am
Location – Hitchcock 224
Members Present – All
Objective – Oral Presentation on aR&D 1 and 2
Tasks Completed –
Oral Presentation for aR&D
Tasks to be Completed –
Testing for Performance Test 2
Start CDR draft
Committee Meeting 2
Meeting 21
Date – 3/25/19
Time – 8:00 am
Location – Hitchcock 308
Members Present – All
Objective – Work on Performance Test 2 code
Tasks Completed –
Performance Test 2 code
Tasks to be Completed –
Performance Test 2
CDR draft
Committee Meeting 2
Meeting 22
Date – 3/26/19
Time – 4:30 pm
Location – Morrison tower lobby
Members Present – All
Objective – Write/assign parts for the CDR draft
Tasks Completed – assign roles for the CDR draft
Nick – Conclusions and recommendations, results
Dillon – Discussion, experimental methodologies, and solidworks files
Ethan – Create schedule, organize appendices and introduction
Tasks To Be Completed – Progress report 3
Meeting 23
Date – 3/27/19
Time – 8:00 am
Location – Hitchcock 308
Members Present – All
Objective – Complete Performance Test 2
Tasks Completed –
Performance Test 2
Tasks to be Completed –
CDR Draft
Committee Meeting 2
Meeting 24
Date – 3/29/19
Time – 8:00 am
Location – Hitchcock 224
Members Present – All
Objective – Committee Meetings and work on CDR
Tasks Completed –
Committee Meetings finished
CDR draft completed
Tasks to be Completed –
aR&D 3 methodologies
Performance Test 3