Meeting 18

Date and Time: Monday April 1, 2019 8:00am-8:55am

Location: Hitchcock 308

Members in Attendance: Yonis, Brian and Korey

Goal: continue experimentation into the effect of weight on energy.

Completed Tasks: No tasks completed.

Tasks to be Completed:

  • data analysis/documentation for aR&D3

Project Timeline: The lab period on Wednesday April 3, 2019 should be spent collecting the rest of the data. Any remaining time in lab should be spent completing the data analysis and documentation for aR&D3. The next task is to complete the final performance test by Wednesday April 10, 2019. The third progress report and oral presentation draft are both due on Monday April 8, 2019.

Decisions: No decisions made.

 

Meeting 19

Date and Time: Wednesday April 3, 2019 8:00am-8:55am

Location:  Hitchcock 308

Members in Attendance:  Yonis, Brian and Korey

Goal: to complete data collection for aR&D3

Completed Tasks: 

  • data collection for aR&D3
  • data analysis for aR&D3 was started

Tasks to be Completed:

  • progress report 3
  • oral presentation poster rough draft
  • data analysis and conclusions from aR&D3

Project Timeline: The progress report, poster rough draft, and data analysis/conclusions for aR&D3 should be done and turned in by the start of the lab period on Monday April 8, 2019. The final performance test is due Wednesday April 10, 2019.

Decisions: Brian will work on poster draft. Yonis and Korey will work on progress report 3.

 

Meeting 20

Date and Time: Friday April 5, 2019 8:00am-9:20am

Location:  Hitchcock 224

Members in Attendance:  Yonis, Brian and Korey

Goal: to complete code for the final performance test

Completed Tasks:

  • code for final performance test

Tasks to be Completed:

  • progress report 3
  • oral presentation poster draft

Project Timeline:  Both the third progress report and poster draft for the final oral presentation are due before lab on Monday April 8, 2019.

Decisions: Brian will work on poster draft. Yonis and Korey will work on progress report 3.

 

Meeting 21

Date and Time: Monday April 8, 2019 8:00am-8:55am

Location: Hitchcock 308

Members in Attendance: Yonis, Brian and Korey

Goal: To complete coding for room 308 for the final performance test

Completed Tasks:

  • Code for Room 308.

Tasks to be Completed:

  • after feedback is returned, make necessary changes to oral presentation poster
  • after feedback is returned, make necessary changes to CDR and add recent material

Project Timeline: The final draft of the oral presentation poster is due Monday April 15, 2019. The oral presentation itself will be completed Wednesday April 17, 2019 or Friday April 19, 2019. The final CDR and final website update is due Friday April 19, 2019.

Decisions: No major decisions.

 

Meeting 22

Date and Time: Wednesday April 10, 2019 8:00am-8:55am

Location: Hitchcock 308

Members in Attendance: Yonis, Brian and Korey

Goal:  To complete at least one of the final performance tests

Completed Tasks:

  • One performance test.

Tasks to be Completed:

  • day 2 of the final performance test
  • oral presentation final draft

Project Timeline: Day 2 of the final performance test will be completed by the end of the lab period on April 12, 2019. The final draft of the oral presentation is due before the lab period on Monday April 15, 2019

Decisions: Yonis will make changes to the oral presentation rough draft so it is completed by Monday. Korey and Brian will double check the final draft before it is turned in before Monday April 15, 2019 at 8:00am.

 

Meeting 23

Date and Time: Friday April 12, 2019 8:00am-9:20am

Location: Hitchcock 224

Members in Attendance: Yonis, Brian and Korey

Goal: Completion of Final Performance Test.

Completed Tasks:

day 2 of the final performance test

Tasks to be Completed:

  • Data analysis for the final performance test to be used on the oral presentation poster.
  • Final documentation (CDR and website) for the entire AEV project.

Project Timeline: The final version of the oral presentation poster is due Monday April 12, 2019. All final documentation is due Friday April 19, 2019.

Decisions: Yonis will collect and analyze all data and fill out final budget. Korey and Brian will finish the final poster for the oral presentation.

 

Meeting 24

Date and Time: Monday April 15, 2019 8:00am-8:55am

Location: Hitchcock 308

Members in Attendance: Yonis, Brian and Korey

Goal: Return Kit

Completed Tasks:

  • AEV disassembled and kit returned

Tasks to be Completed:

  • Final presentation
  • CDR final draft
  • Final website update

Project Timeline:  The oral presentation poster has to be completed by midnight today, Monday April 15, 2019. The CDR final draft and final website is due Friday April 19, 2019.

Decisions: Korey will finish the oral presentation poster. Yonis will complete the CDR. Brian will finish the final website update.