Meeting 1
Date and Time: Friday, Jan 11th at 9:00 am – 10 am
Location: Hitchcock Rm 216
Members in Attendance: Yonis, Brian, Angelo, Korey
Goal: Introduction to group members, and to share contact information. Our goals also included to work on Application problems and to research and discuss the ahead material (AEV project)
Completed Tasks: Application’s 02A & B
Tasks to be Completed:
- Establish an efficient way of communication and file sharing
- Create team meeting minutes
- Initial Website design and info
Project Timeline:
Refer to: https://osu.app.box.com/s/3mal1rsekfbvd5oflbhmbuahawq9oc8p
Decisions: We decided to communicate through the group chat this first week to plan the website updates.
website updates.
Meeting 2
Date and Time: Friday, Jan 18th at 8:00 am – 9:20 am
Location: Hitchcock Rm 224
Members in Attendance: Yonis, Brian, Angelo, Korey
Goal: Distribute AEV kits, complete and submit AEV kit policy forms.
Completed Tasks: Lab Week 02 module – we reviewed the AEV kits and checked inventory. Also completed all paperwork – the AEV Kit Policy AEV Kit Label. Finished construction.
Tasks to be Completed:
- Sign up for lab time to keep working
Project Timeline:
Refer to: https://osu.app.box.com/s/3mal1rsekfbvd5oflbhmbuahawq9oc8p
Decisions: No major decisions made.