PROJECT SCHEDULE

 

Task Start Date Finish Date Due Date Primary Person Secondary Person Est. Hours % Completed
Grant Proposal 2/9/19 2/14/19 2/14/19 Jeff, Nick Tiana, Samira 2 100
Progress Report 1 2/9/19 2/14/19 2/15/19 All 4 100
Committee Meeting 2/20/19 2/22/19 2/22/19 All 0.5 100
Advance R&D 1 2/22/19 3/1/19 3/1/19 Nick, Jeff Samira 3.5 100
Advance R&D 2 3/3/10 3/7/19 3/8/19 Nick,

Jeff

Samira 4 100
Performance Test 1 3/8/19 3/19/19 3/19/19 Nick Jeff 2 100
GOAL: Secure wires and propellor motors 3/18/19 3/19/19 3/19/19 Jeff Nick, Samira 0.5 100
Advance R&D Presentation 3/18/19 3/19/19 Lab 13 Samira Jeff, Nick 2 100
Performance Test 2 3/20/19 3/28/19 3/28/19 Nick, Jeff Samira 2 100
Advanced R&D 3 3/26/19 3/29/19 Lab 18 Jeff Samira, Nick 2 100
Final Deliverables 3/29/19 4/3/19 Lab 19 Nick Jeff, Samira 5 100
Final Performance Test 4/2/19 4/5/19 Lab 21 Nick Jeff 3 100
Oral Presentation 4/1/19 4/14/19 Lab 24 Samira Nick,Jeff 3 100
Progress Report 2 3/3/19 3/18/19 3/19/19 Samira Nick, Jeff 5 100
Website 3 Update 3/3/19 3/7/19 3/8/19 Samira Nick, Jeff 2 100
CDR (draft) 3/20/19 3/21/19 Lab 14 Jeff Nick, Samira 3 100
Team Eval 2 3/25/19 3/27/19 Lab 16 All 0.5 100
Committee Meetings 2 3/25/19 3/27/19 Lab 16 All 1 100
Progress Report 3 3/29/19 4/3/19 Lab 19 Jeff Nick, Samira 5 100
Final Oral Presentation Draft 3/29/19 4/4/19 Lab 21 Samira Nick, Jeff 2 100
Final Team Eval 4/15/19 4/17/19 Lab 25 All 0.5 100
CDR 3/22/19 4/17/19 Lab 25 Jeff Samira, Nick 7 10 0
Final Website 4/11/19 4/17/19 Lab 25 Samira Jeff, Nick 4 100
Cost Report 4/14/19 4/19/19 Nick Jeff, Samira 1 100
GOAL: use less than or equal to 75% of the budget 2/19/19 4/18/19 Lab 25 ALL Throughout 100
GOAL: finish assignments 24 hours before due date 4/7/19 Lab 25 ALL Throughout 100