C. Project Schedule

The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done.  This document will be updated throughout the course of the project.

Task Start

Date

Finish

Date

Due

Date

Primary

Person

Secondary

Person

 Est.

Hrs

%

Done

Connect Four

Flowchart

11/1 11/1 11/5 Andy

Dong

1 100%

Connect Four

Code

11/1 11/8 11/19 Andy

Dong

6 100%

“Pitch” Video

 

“Pitch” Video Slides

 

11/4 11/4 11/5 Andy

Dong

1 100%

Business Plan

(Interviews)

10/29 12/3 Andy

Dong

66%

Software

Documentation

(Connect Four)

11/12 11/12 12/3 Andy

Dong

2 100%

User Interview 1

 

10/28 10/28 12/3 Andy

Dong

Leroy

Michael

0.5 100%

User Interview 2

 

11/12 11/12 12/3 Andy

Dong

Chris

Farina

0.5 100%

Guitar Hero

Pseudo-code

10/26 11/4 11/19 Andrew Kolarits 10 hrs 100%

Guitar Hero

Code

10/26 11/19 11/19 Andrew Kolarits 24 hrs 100%

Software

Documentation

(Guitar Hero)

11/30 12/1 12/3 Andrew Kolarits 2 hrs  100%

Executive Summary

 

11/30 11/30 12/3 Andy

Dong

1 100%

Full Report

(intro, conclusion, etc)

11/30 11/30 12/3 Andy

Dong

2 100%