Schedule

Task Start Finish Due Date Alyssa Ryan James Quinton % Complete
Prototype 1 Construction 3-Mar 3-Mar 3-Mar x x 100
Prototype 1 Testing 7-Mar 20-Mar 20-Mar x x x x 100
Prototype 2 Construction 21-Mar 21-Mar 28-Mar x x 100
Prototype 2 Testing 21-Mar 21-Mar 28-Mar x x x 100
Winnibago Solidworks Model 3-Mar 23-Mar 23-Mar x 100
AEV Code 7-Mar 13-Apr 13-Apr x 100
Winnibago Construction 21-Mar 11-Apr 13-Apr x x x x 100
Winnibago Testing 13-Apr 13-Apr 13-Apr x x x x 100
PDR 23-Mar 27-Mar 28-Mar x x x x 100
CDR & Presentation 13-Apr 20-Apr 20-Apr x x x x 100