C. Project Schedule

The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done.  This document will be updated throughout the course of the project.

 

Task Start

Date

Finish

Date

Due

Date

Primary

Person

Secondary

Person

 Est.

Hrs

%

Done

 

Designing the algorithm

 November 7th November 7th November 8th  Karthik Pillalamarri  Weilie Lin 1 hr 100%
Coding

 

 November 10th November 12th  November 15th  Karthik Pillalamarri Weilie Lin 5 hrs  100%
Debugging

 

 November 13th  November

14th

 November 15th Karthik Pillalamarri Chenchen Zhou 1 hrs 100%
Software Documentation/Table of contents

 

 December 2nd  December 4th  December 5th  Chenchen Zhou Karthik Pillalamarri 5 hrs 100%
 

Business Plan/Executive summary

 December 2nd  December 4th  December 5th  Weilie Lin Karthik Pillalamarri 3 hrs 100%
 

Project Management

 December 2nd  December 4th  December 5th Chenchen Zhou Weilie Lin 3 hrs 100%
 

Introduction of the Video

 December 4th  December 4th December 5th Karthik Pillalamarri Chenchen Zhou 2 hrs 100%
Act in Advertisement

 

 December 4th  December 4th  December 5th  All  1 hr 100%
Filming the Advertisement

 

 December 4th  December 4th  December 5th All 1 hr 100%
Final Checking December 4th December 4th December 5th All  1 hr 100%