The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done. This document will be updated throughout the course of the project.
Task | Start
Date |
Finish
Date |
Due
Date |
Primary
Person |
Secondary
Person |
Est.
Hrs |
%
Done |
Designing the algorithm |
November 7th | November 7th | November 8th | Karthik Pillalamarri | Weilie Lin | 1 hr | 100% |
Coding
|
November 10th | November 12th | November 15th | Karthik Pillalamarri | Weilie Lin | 5 hrs | 100% |
Debugging
|
November 13th | November
14th |
November 15th | Karthik Pillalamarri | Chenchen Zhou | 1 hrs | 100% |
Software Documentation/Table of contents
|
December 2nd | December 4th | December 5th | Chenchen Zhou | Karthik Pillalamarri | 5 hrs | 100% |
Business Plan/Executive summary |
December 2nd | December 4th | December 5th | Weilie Lin | Karthik Pillalamarri | 3 hrs | 100% |
Project Management |
December 2nd | December 4th | December 5th | Chenchen Zhou | Weilie Lin | 3 hrs | 100% |
Introduction of the Video |
December 4th | December 4th | December 5th | Karthik Pillalamarri | Chenchen Zhou | 2 hrs | 100% |
Act in Advertisement
|
December 4th | December 4th | December 5th | All | 1 hr | 100% | |
Filming the Advertisement
|
December 4th | December 4th | December 5th | All | 1 hr | 100% | |
Final Checking | December 4th | December 4th | December 5th | All | 1 hr | 100% | |