Meeting 23

March 7, 2018
3:00 pm
Hitchcock Hall Room 214

Meeting Agenda: 

  1. Complete Performance Test 3
  2. Start electrical documentation
  3. Start preparing for Performance Test 4

Meeting Notes: 

Everyone was present for this meeting. The whole group worked towards successfully completing Performance Test 3. Shyon started the electrical documentation. Meghan worked on documentation and the website.

Future Actions:

  1. Finish electrical documentation
  2. Start final report draft
  3. Prepare for Performance Test 4

Meeting 22

March 5, 2018
3:00 pm
Hitchcock Hall Room 214

Meeting Agenda:

  1. Board Meeting #2 (Teamwork)
  2. Get robot working for performance test 3
  3. Finish exploration
  4. Mid-semester feedback

Meeting Notes: 

Everyone was present for this meeting. Tom and Dean worked on Performance Test 3 preparation. Meghan worked on the website and documentation, as well as mid-semester feedback. Shyon prepared for and went to the teamwork board meeting, bringing back feedback to the group.

Future Actions:

  1. Complete Performance Test 3
  2. Start electrical documentation

Meeting 21

March 4, 2018
2:00 pm
Hitchcock Hall Room 214

Meeting Agenda: 

  1. Get data logging from exploration 3 done
  2. Start working on Performance Test 3

Meeting Notes:

Only Tom and Dean were present. Tom started testing for Performance Test 3 using only the bump switch, as the line following kit was being re-soldered. With Dean, he cut the motor wires to get a stronger connection with the motor ports. Dean re-soldered the line following kit, added the appropriate resistors to it. He mounted a bump switch to the robot for testing while re-doing the line following kit.

Future Actions: 

  1. Prepare for board meeting
  2. Prepare for Performance Test 3
  3. Finish exploration
  4. Mid-semester feedback