Design Schedule 3/26/14

Design Schedule Last revised 3/26/14 By: Luke Burgett
1 Task Name/Number Start Date Finish Date Deadline Primary Member Secondary Member est. time actual time status of task
2 Brainstorming R01 1/26/2014 1/26/2014 1/29/2014 Luke Burgett Grant Oehler 1hr 1hr 100% Symbols
3 Design Matrix R02 1/26/2014 1/26/2014 1/29/2014 Rhys Davis Grant Oehler 4hrs 4hrs 100% R# = Robot assignment
4 Design schedule R03-1. 1/26/2014 1/29/2014 1/31/2014 Luke Burgett Ryan McLaughlin 3hrs 1 hr 100% PT# = Pefromance Test
5 Mockups PT1. 1/24/2014 1/30/2014 1/31/2014 Grant Oehler Luke Burgett 6hrs 2hr 100% I# = Individual assignments
6 Drivetrain analysis R05-1 1/27/2014 2/1/2014 2/3/2014 Ryan McLaughlin Luke Burgett 2hrs 2 hrs 100%
7 Chassis Construction I1 2/2/2014 2/7/2014 2/7/2014 Luke Burgett Grant Oehler 2hrs 3 hrs 100%
8 Drivetrain construction I2 2/5/2014 2/6/2014 2/7/2014 Ryan McLaughlin Luke Burgett 3hrs 3 hrs 100%
9 PT2 (Drive Up Ramp.) 1/31/2014 2/6/2014 2/7/2014 Rhys Davis Ryan McLaughlin 2hrs 2 hrs 100%
10 Pseudocode/Flowchart R06-1 2/5/2014 2/12/2014 2/14/2014 Rhys Davis N/A 4hrs 3 hrs 100%
11 Progress Report R06-2 2/5/2014 2/19/2014 2/21/2014 Ryan McLaughlin Grant Oehler 5hrs 4 hrs 100%
12 Proteus Mount I3 2/7/2014 2/10/2014 2/12/2014 Luke Burgett N/A 2hrs 2 hrs 100%
13 Code to read start light and hit button 2/6/2014 2/12/2014 2/14/2012 Rhys Davis Luke Burgett 2hrs 2 hrs 100%
14 PT3 (Start Light and Oven Button) 2/7/2014 2/14/2014 2/14/2014 Grant Oehler Ryan McLaughlin 5hrs 5 hrs 100%
15 Code for Course Layout I4 2/13/2014 2/18/2014 2/20/2014 Rhys Davis Ryan McLaughlin 4hrs 3 hrs 100%
16 Forklift Construction I5 2/14/2014 2/19/2014 2/21/2014 Grant Oehler Luke Burgett 4hrs 2 hrs 100%
17 Motor testing for Forklift I6 2/20/2014 2/24/2014 2/24/2014 Luke Burgett Rhys Davis 2hrs 1 hr 100%
18 Forklift code I7 2/20/2014 2/23/2014 2/24/2014 Rhys Davis Grant Oehler 1hr 30 mins 100%
19 PT4( Switch and Pin) 2/20/2014 2/23/2014 2/24/2014 Ryan Davis Ryan McLaughlin 3hrs 5 hrs 100%
20 Intro – R10-1 2/24/2014 3/1/2014 3/3/2014 ALL ALL 2hrs 1 hr 100%
21 R10-2 3/1/2014 3/3/2014 3/7/2014 ALL ALL 2hrs 2 hrs 100%
22 PT5 (Pull Pin and down ramp) 2/28/2014 2/28/2014 2/28/2014 ALL ALL 3hrs 4 hrs 100%
23 Final Report Draft 1 R11 3/3/2014 3/17/2014 3/19/2014 Luke Burgett Grant Oehler 4hrs 3 hrs 100%
24 Electrical Sketches R12 3/3/2014 3/23/2014 3/24/2014 Rhys Davis Grant Oehler 3hrs 2hrs 100%
25 PT6(Skid) 3/7/2014 3/7/2014 3/7/2014 Ryan McLaughlin Luke Burgett 3hrs 4 hrs 100%
26 Construct dumping bin for scoop I8 3/15/2014 3/20/2014 3/21/2014 Luke Burgett Grant Oehler 2hrs 1 hrs 100%
27 Gear switch for Forklift/scoop I9 3/10/2014 3/20/2014 3/21/2014 Ryan McLaughlin Rhys Davis 3hrs 2 hrs 100%
28 Oral Report Outline R14 3/17/2014 4/6/2014 4/7/2014 Rhys Davis Ryan McLaughlin 4hrs 0%
29 Oral Report R16 3/17/2014 4/10/2014 4/10/2014 Grant Oehler Luke Burgett 5hrs 0%
30 Final Report Draft 2 R13 3/19/2014 3/30/2014 3/31/2014 Ryan McLaughlin Rhys Davis 4hrs 5hrs 100%
31 PT7(Read Light, Scoop, Charger) 3/21/2014 3/21/2014 3/21/2014 Luke Burgett Ryan McLaughlin 2hrs 1.5 hrs 100%
32 Individual Competition I10 3/28/2014 3/28/2014 3/28/2014 Grant Oehler Rhys Davis 3hrs 8hrs 100%
33 Working Drawing Set R15 4/7/2014 4/10/2014 4/11/2014 Ryan McLaughlin Grant Oehler 2hrs 0%
34 Final Report R17 3/3/2014 4/20/2014 4/21/2014 Luke Burgett Rhys Davis 5hrs 0%
35 Notebook R18 1/31/2014 4/20/2014 4/21/2014 Grant Oehler Ryan McLaughlin 20hrs 0%