B. Project Schedule

The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done.  This document will be updated throughout the course of the project.

Task Start

Date

Finish

Date

Due

Date

Primary

Person

Secondary

Person

 Est.

Hrs

%

Done

 Program Menu and different options  11/29/18  11/29/18  12/4/18  Jake  Russell  0.5  100%
 Create Map  11/29/18 11/29/18  12/4/18  Jake  Russell  0.5  100%
 Get map to display properly  11/29/18  11/29/18  12/4/18  Jake  Russell  0.5  100%
 Get the ghost logic working  12/1/18  12/3/18  12/4/18  Russell Jake  1 100%
 Get the pacman logic working  12/1/18  12/3/18  12/4/18  Russell  Jake 1 100%
 Get the up, down, left, and right buttons working  12/1/18  12/3/18  12/4/18 Russell  Jake  0.5 100%
 Program the pause button  12/1/18  12/3/18  12/4/18  Russell  Jake  0.5  100%
 Program the stop button  12/1/18  12/3/18  12/4/18  Russell Jake  0.5  100%
 Get the oranges to display 12/1/18 12/3/18  12/4/18  Russell  Jake  0.5  100%
 Program the oranges to   disappear if pacman runs into them  12/1/18  12/3/18  12/4/18  Russell Jake 1  100%
 Get the program to recognize when the oranges are gone  12/2/18  12/3/18  12/4/18  Russell  Jake 1  100%
 Get the program to recognize when the player loses  12/2/18  12/3/18  12/4/18 Russell Jake  0.5  100%
 Get the end game display screen working  12/2/18 12/3/18  12/4/18 Jake  Russell  0.5  100%
 Get the leader board screen and point system working  12/2/18  12/3/18  12/4/18  Jake  Russell  0.5  100%
 Program rules and instructions on menu  12/2/18  12/3/18  12/4/18  Russell Jake  0.5  100%
 Program reset statistics on menu  12/2/18  12/3/18  12/4/18  Jake  Russell  0.5  100%
 Program the credits on menu  12/2/18  12/3/18  12/4/18  Jake  Russell  0.5  100%
 Add additional comments to explain the code  12/2/18  12/3/18  12/4/18  Russell  Jake  0.5  100%