Week 6

Location: Hitchcock Hall | Time: 12:45 PM | Date: 2/14/18 | Attendees: Taylor, Kendall, Derek, Szhihan

Topics Discussed and Tasks Completed:

Group: Completed committee meetings

Group: Discussed what was learned in each meeting and made adjustments to various parts of project as needed

Group: Prepared for battery testing lab

Kendall: Completed grant proposal

 

Upcoming tasks:

Group P must complete the Battery testingĀ  lab next class and begin to prepare for the A R&D Presentation in two weeks.