C. Project Schedule

The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done.  This document will be updated throughout the course of the project.

Task Start

Date

Finish

Date

Due

Date

Primary

Person

Secondary

Person

 Est.

Hrs

%

Done

Pitch Power Point

 

11/6/23 11/13/23 11/14/23 Gaby Tyler 1 100%
SDP Lab 3 Check In

 

11/13/23 11/14/23 11/14/23 Tyler Gaby 2 100%
Video Presentation

 

11/13/23 11/29/23 11/28/23 Alex Gaby 1  100%
Creating Sprites

 

11/20/23 11/21/23 11/28/23 Tyler Alex 1  100%
Coding Gameplay

 

11/13/23 11/27/23 11/28/23 Alex Gaby 3  100%
Coding Start Up

 

11/13/23 11/17/23 11/28/23 Gaby Alex 2  100%
Coding Game Completion

 

11/18/23 11/20/23 11/28/23 Alex Tyler 2  100%
Project Notebook

 

10/31/23 12/3/23 12/3/23 All members 4  100%