C. Project Schedule

The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done.  This document will be updated throughout the course of the project.

Task Start

Date

Finish

Date

Due

Date

Primary

Person

Secondary

Person

 Est.

Hrs

%

Done

Programming the Game

 

11/14/20 12/4/20 12/4/20 Hayden Frea Aayush Patel and Joshua Roemer 10 100%
Documentation

 

11/10/20 12/4/20 12/4/20 Aayush Patel Hayden Frea and Joshua Roemer 6 100%
Video Creation

 

12/1/20 12/4/20 12/4/20 Joshua Roemer Hayden Frea and Aayush Patel 1 100%