The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done. This document will be updated throughout the course of the project.
Task | Start
Date |
Finish
Date |
Due
Date |
Primary
Person |
Secondary
Person |
Est.
Hrs |
%
Done |
Deciding on game(s) |
10/31/19 | 10/31/19 | 10/31/19 | Owen, Alvin, Jared, and Camden | N/A | 1 | 100 |
Flowchart Draft |
10/31/19 | 11/6/19 | 11/7/19 | Camden | Jared | 2 | 100 |
Work on Connect four code |
11/7/19 | 11/7/19 | 11/14/19 | Owen | Jared | 6 | 100 |
Work on Text based Adventure Game
|
11/7/19 | 11/7/19 | 11/14/19 | Alvin | Camden | 3 | 100 |
Finish Connect four code |
11/13/19 | 11/14/19 | 11/21/19 | Owen | Jared | 4 | 100 |
Software project video slides draft
|
11/13/19 | 11/13/19 | 11/14/19 | Owen, Jared, Camden | Alvin | 1 | 100 |
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|