C. Project Schedule

The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done.  This document will be updated throughout the course of the project.

Task Start

Date

Finish

Date

Due

Date

Primary

Person

Secondary

Person

 Est.

Hrs

%

Done

Code Simple Dice Game (High Low)

 

Nov 1 Nov 20 Nov 22 Chuck Katie 2 hours 100
Code Tenzi

 

Nov 1 Nov 20 Nov 22 Chuck Yasmine 2 hours 100
Test Code

 

Nov 20 Nov 22 Nov 22 Katie Yasmine 1 hour 100
 

Documentation:

Dec 3 100
A. Introduction, B. User Manual, C. Program Description for Developers, Electronic Print Advertisement

 

Nov 13 Dec 2 Dec 3 Kayla Yasmine 4 hours 100
C. Program Design for developers, F. Discussion, G.Conclusions and recommendations H. References

 

Nov 13 Dec 2 Dec 3 Yasmine Kayla 4 hours 100
D. Flowchart/psuedocode, E. final code with comments, Videos

 

Nov 13 Dec 2 Dec 3 Katie Yasmine 4 hours 100
 E. upload final code with comments

 

Nov 13 Dec 2 Dec 3 Chuck Katie 1 hour 100