The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done. This document will be updated throughout the course of the project.
Task | Start
Date |
Finish
Date |
Due
Date |
Primary
Person |
Secondary
Person |
Est.
Hrs |
%
Done |
Code Simple Dice Game (High Low)
|
Nov 1 | Nov 20 | Nov 22 | Chuck | Katie | 2 hours | 100 |
Code Tenzi
|
Nov 1 | Nov 20 | Nov 22 | Chuck | Yasmine | 2 hours | 100 |
Test Code
|
Nov 20 | Nov 22 | Nov 22 | Katie | Yasmine | 1 hour | 100 |
Documentation: |
Dec 3 | 100 | |||||
A. Introduction, B. User Manual, C. Program Description for Developers, Electronic Print Advertisement
|
Nov 13 | Dec 2 | Dec 3 | Kayla | Yasmine | 4 hours | 100 |
C. Program Design for developers, F. Discussion, G.Conclusions and recommendations H. References
|
Nov 13 | Dec 2 | Dec 3 | Yasmine | Kayla | 4 hours | 100 |
D. Flowchart/psuedocode, E. final code with comments, Videos
|
Nov 13 | Dec 2 | Dec 3 | Katie | Yasmine | 4 hours | 100 |
E. upload final code with comments
|
Nov 13 | Dec 2 | Dec 3 | Chuck | Katie | 1 hour | 100 |
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|
|||||||
|