C. Project Schedule

The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done.  This document will be updated throughout the course of the project.

Task Start

Date

Finish

Date

Due

Date

Primary

Person

Secondary

Person

 Est.

Hrs

%

Done

Tic-Tac-Toe 11/6 11/19 11/19 Andrew Olivia 30 100
Connect 4 11/9 11/14 11/19 Michael Aleysha 20 40
Hangman 11/15 11/19 11/19 Michael Aleysha 15 80
Team Working Agreement 11/4 11/4 11/5 Michael .1 100
Individual Responsibility Agreement 11/4 11/4 11/5 Michael .5 100
Interview #1 11/5 11/5 11/5 Olivia Michael .4 100
Flowchart 11/4 11/5 11/5 Andrew Aleysha 1 100
Interview #2 11/12 11/12 11/12 Olivia Michael .3 100