C. Project Schedule

The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done.  This document will be updated throughout the course of the project.

Task Start

Date

Finish

Date

Due

Date

Primary

Person

Secondary

Person

 Est.

Hrs

%

Done

Create u.osu.edu Account

Initial Decision on Games

11/1/19 11/1/19 11/1/19 Team Effort

(in class)

n/a 1 100%
User Interview 1

User Identification

11/1/19 11/1/19 11/8/19 Team Effort

(in class)

n/a 1 100%
Team Working Agreement

 

11/3/19 11/3/19 11/8/19 Team Effort n/a 30 min 100%
Individual Responsibility Statement

 

11/3/19 11/3/19 11/8/19 Team Effort n/a 15 min 100%
Initial Flowcharts

 

11/4/19 11/4/19 11/8/19 Rachel, Amy, Amanda n/a 30 min 100%
Work on Code

 

11/4/19 11/22/19 11/22/19 Rachel, Amanda (Battleship)

Amy (Connect 4)

n/a 6 100%
User Interview 2

 

11/13/19 11/13/19 11/15/19 Amy n/a 45 min 100%
Final Software Design Project Plan 11/15/19 11/15/19 11/15/19 Team Effort n/a 15 min 100%
Draft PPT Slides

 

11/15/19 11/15/19 11/15/19 Rachel n/a 30 min 100%
Final Video

 

11/29/19 11/29/19 12/3/19 Team Effort n/a 1 100%
Electronic Advertisement

 

12/2/19 12/2/19 12/4/19 Andrew Rachel 1 100%
User Manual

 

11/22/19 11/22/19 12/4/19 Andrew n/a 30 min 100%
Program Description for Developers

 

12/2/19 12/2/19 12/4/19 Amy Amanda 1 100%
Final Flowchart (Battleship)

 

12/1/19 12/1/19 12/4/19 Rachel Amanda 1 100%
Final Flowchart (Connect 4)

 

12/1/19 12/1/19 12/4/19 Amy Amanda 1 100%
 

Discussion

12/3/19 12/3/19 12/4/19 Amanda Amy 1.5 100%
Conclusion and Recommendations 12/3/19 12/3/19 12/4/19 Amanda Rachel 30 min 100%