C. Project Schedule

The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done.  This document will be updated throughout the course of the project.

 

 

Task Start

Date

Finish

Date

Due

Date

Primary

Person

Secondary

Person

 Est.

Hrs

%

Done

Create Website

Team and Individual Responsibility Agreement

 

10/31 10/31 11/7 Jillian Areebah 30 mins 100
User Interview 1

 

10/31 10/31 11/7 Sam 30 mins  100
Coding Connect Four

 

11/17 11/21 12/4 Henry Sam 6 hours  100
Coding Under and Over Seven

 

11/7 11/21 12/4 Areebah Henry 1. 5 hours  100
User Interview 2

 

11/21 11/21 11/21 Sam Jillian 30 mins  100
Electronic/Print Advertisement

 

11/21 11/31 11/4 Areebah Sam 1 hour  100
Video advertisement

 

11/21 12/2 12/4 Henry Jillian 2.5 hours  100
Welcome Page

  • Table of contents
  • Executive Summary

 

11/21 12/2 12/4 Areebah Jillian 1 hour  100
Project Management

  • Team and Individual Agreement
  • Project Schedule
  • Meeting Notes

 

 

10/31 12/2 12/4 Areebah Jillian 1.5 hours  100
Business Plan

  • Print Advertisement
  • Video Advertisement

 

 

10/7 11/28 12/4 Henry Areebah 2 hours  100
Software Documentation

  • Introduction
  • User Manual
  • Program Description

 

11/14 11/28 12/4 Henry/Jillian Areebah 2 hours  100
Software Documentation

  • Flowchart

 

10/7 11/7 12/4 Sam 1 hour  100
Software Documentation

  • Final Program with comments
  • Brief Discussion
  • Conclusion and Recommendation
11/21 12/2 12/4 Sam Jillian 2.5 hours  100