The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done. This document will be updated throughout the course of the project.
Task | Start
Date |
Finish
Date |
Due
Date |
Primary
Person |
Secondary
Person |
Est.
Hrs |
%
Done |
Program Connect 4 | 10/31/18 | 11/13/18 | 11/28/18 | Ryan | Megan | 3 | 100% |
Program Over 7/Under 7 | 11/8/18 | 11/12/18 | 11/28/18 | Hanyuan | Jiwoong | 1 | 100% |
Connect 4 Flowchart | 11/6/18 | 11/6/18 | 11/7/18 | Ryan | N/A | 0.5 | 100% |
Over 7/ Under 7 Flowchart | 11/6/18 | 11/7/18 | 11/7/18 | Hanyuan | N/A | 0.5 | 100% |
Team Working Agreement | 10/31/18 | 10/31/18 | 11/7/18 | Megan | Ryan | 0.5 | 100% |
Video Filming | 11/19/18 | 11/19/18 | 11/28/18 | Everyone | N/A | 1.5 | 100% |
Video Editing | 11/27/18 | 11/27/18 | 11/28/18 | Megan | N/A | 2.5 | 100% |