Task | Start
Date |
Finish
Date |
Due
Date |
Primary
Person |
Secondary
Person |
Est.
Hrs |
%
Done |
|
11/01/18 | 11/01/18 | 12/05/18 | All | All | 1 | 100% |
|
11/08/18 | 11/08/18 | 12/05/18 | Flowchart and Algorithm: Camille & Shobitha
Fill out team working agreement: All |
Benny and Malle | 2 | 25-flowchart
100-agreement |
|
11/15/188 | 11/15/18 | 12/05/18 | storyboard: Camille
Interview: Malle Continue coding: Benny & Shobitha |
2 | 100-storyboard
interview-100 50- coding |
|
|
11/24/18 | 11/24/18 | 12/05/18 | coding: Benny
Algorithm: Shobitha & Camille |
2 | 75- coding
100- algorithms |
|
|
11/26/18 | 11/26/18 | 12/05/18 | coding-Benny
video acting- all Manuals- Camille & Shobitha |
3 | coding-100
film video-75 manuals-50 |
|
|
11/29/18 | 11/29/18 | 12/05/18 | Project plan- Camille
Film/acting- all Discussion/ Conclusion- Malle |
3 | plan-100
film-100 conclusion/discussion-25 |
|
|
12/02/18 | 12/02/18 | 12/05/18 | Edit- Shobitha | 3 | edit-50 | |
|
12/03/18 | 12/03/18 | 12/05/18 | manuals-Camille
Edit- Shobitha |
3 | edit-75
manuals- 100 |
|
|
12/04/18 | 12/04/18 | 12/08/18 | edit- Shobitha
Executive- Malle Comments- Malle, Benny |
3 | edit-100
summary-100 comments-100 |
|
|
12/05/18 | 12/05/18 | 12/05/18 | Organizing- Camille, Shobitha
Code-Benny |
2 | 100-organizing
100- code |
|