C. Project Schedule

The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done.  This document will be updated throughout the course of the project.

Task Start

Date

Finish

Date

Due

Date

Primary

Person

Secondary

Person

 Est.

Hrs

%

Done

Create an u.osu.edu account

 11/1/18 11/1/18 11/1/18  Hunter Mastin N/A 30 min  100%

Initial Decision on Games

 11/1/18  11/1/18  11/1/18 Tom Kennedy & Hunter Mastin Alex Corpuz & Maddi Prenger  10 min  100%

User Interview #1

 11/1/18  11/7/18 11/1/18 Maddi Prenger Tom Kennedy  20 min  100%
 Team Working Agreement  8/28/18 8/30/18 11/8/18 Alex Corpuz Tom Kennedy, Maddi Prenger, & Hunter Mastin 30 min 100%
Individual Responsibility  Agreement 11/1/18 11/7/18 11/8/18  Alex Corpuz  Maddi Prenger 15 min 100%
Algorithm Draft  11/7/18  11/7/18 11/8/18  Maddi Prenger & Alex Corpuz Tom Kennedy & Hunter Mastin 1 hr 100%
 Draft Video Slides 11/8/18 11/15/18  11/15/18  Alex Corpuz Maddi Prenger 45 min 100%
 User Interview #2 11/14/18  11/15/18  11/15/18 Tom Kennedy Maddi Prenger 15 min 100%
 Final Software Project Plan 11/15/18 11/15/18  11/15/18 Alex Corpuz  N/A 5 min 100%
 Final Codes 11/1/18 11/29/18 11/29/18  Tom Kennedy & Hunter Mastin Maddi Prenger & Alex Corpuz 40 hrs 100%
Documentation 11/15/18  12/4/18 12/5/18 Alex Corpuz & Maddi Prenger Hunter Mastin & Tom Kennedy 20 hrs 100%
Pitch Video 11/28/18  12/2/18 12/3/18 Alex Corpuz & Tom Kennedy Maddi Prenger & Hunter Mastin 5 hrs 100%
Electronic Print Advertisements 11/15/18  11/26/18 12/5/18 Maddi Prenger N/A 45 min 100%