The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done. This document will be updated throughout the course of the project.
Task | Start
Date |
Finish
Date |
Due
Date |
Primary
Person |
Secondary
Person |
Est.
Hrs |
%
Done |
Initial Decision on games | 10-30 | 11-1 | 11-2 | Zane | Dylan | 0.5 | 100 |
Teammate Agreement | 10-30 | 11-1 | 11-2 | Conner | Comfert | 0.5 | 100 |
Individual Responsibility Agreements | 10-30 | 11-1 | 11-2 | Conner | Zane | 0.5 | 100 |
User Interview #1 | 11-5 | 11-5 | 11-2 | Comfert | Conner | 1 | 100 |
Flowcharts | 11-1 | 11-2 | 11-2 | Zane | Dylan | 1.5 | 100 |
Start Script | 11-2 | 11-15 | 11-16 | Dylan | Conner | 6 | 100 |
User Interview #2 | 11-7 | 11-7 | 11-9 | Comfert | Zane | 1 | 100 |
Draft Slides | 11-6 | 11-10 | 11-13 | Conner | Comfert | 2 | 100 |
Video | 12-3 | 12-3 | 12-5 | Dylan | Conner | 2 | 100 |