Team Schedule and Contact Information

Contact Team J

Matthew Caldwell – caldwell.720@osu.edu
John Kim – kim.6465@osu.edu
Jacob Phillips – phillips.1623@osu.edu
Tarun Pilli – pilli.2@osu.edu

Full Semester Schedule

No. Task Start Finish Due Date Est Time Matthew Caldwell Tarun Pilli Jacob Phillips John Kim Percent Done
1 Progress Report for Lab 2 18-January 23-January 24-January 3.0 h 3.0 h 3.0 h 3.0 h 3.0 h 100
2 Sample AEV Construction 23-January 23-January 24-January 1.0 h 1.0 h 1.0 h 100
3 Progress Report for Lab 3 26-January 2-February 3-February 3.0 h 03.0 h 3.0 h 3.0 h 3.0 h 100
4 Revision of the Progress Report for Lab 2 3-February 3-February 7-February 1.0 h 1.0 h 1.0 h 1.0 h 1.0 h 100
5 Progress Report for Lab 4 3-February 6-February 7-February 3.0 h 3.0 h 3.0 h 3.0 h 100
6 Progress Report for Lab 5 7-February 13-February 14-February 4.0 h 4.0 h 4.0 h 4.0 h 4.0 h 100
7 Progress Report for Lab 6 14-February 20-February 21-February 4.0 h 4.0 h 4.0 h 4.0 h 4.0 h 100
8 Preliminary Check of the Project Portfolio 13-February 20-February 21-February 1.0 h 1.0 h 1.0 h 1.0 h 1.0 h 100
9 Executive Summary for New Lab 28-February 6-March 7-March 3.0 h 3.0 h 3.0 h 3.0 h 3.0 h 100
10 Progress Report for Lab 8 7-March 9-March 10-March 2.0 h 2.0 h 2.0 h 2.0 h 2.0 h 100
11 AEV 1 Construction 7-March 20-March 27-March 1.0 h 1.0 h 1.0 h 1.0 h 1.0 h 100
12 AEV 1 Testing 20-March 21-March 27-March 0.5 h 0.5 h 0.5 h 0.5 h 0.5 h 100
13 AEV 2 Construction 21-March 24-March 27-March 0.5 h 0.5 h 0.5 h 0.5 h 0.5 h 100
14 AEV 2 Testing 24-March 24-March 27-March 0.5 h 0.5 h 0.5 h 0.5 h 0.5 h 100
15 AEV Solid Works Models 21-March 25-March 27-March 2.0 h 2.0 h 100
16 Preliminary Design Report 21-March 26-March 27-March 7.0 h 6.0 h 6.0 h 1.0 h 100
17 Progress Report for Lab 10 31-March 3-April 4-April 3.0 h 3.0 h 3.0 h 3.0 h 3.0 h 100
18 Oral Presentation Draft 3-April 6-April 7-April 2.0 h 2.0 h 2.0 h 100
19 Progress Report for Lab 11 7-April 9-April 10-April 2.0 h 2.0 h 2.0 h 2.0 h 2.0 100
20 Oral Presentation 3-April 17-April 18-April 3.0 h 3.0 h 3.0 h 3.0 h 3.0 h 100
21 Critical Design Report 10-April 20-April 21-April 6.0 h 6.0 h 6.0 h 2.0 h 1.0 h 100
22 Project Portfolio 13-February 20-April 21-April 3.0 h 3.0 h 3.0 3.0 h 3.0 100