The objectives of this session are to develop the prototype AEV, complete the progress report, and update the website.

Tasks completed from previous week or last meeting

  • AEV assembly was completed – all
  • Individual AEV prototype design – all
  • AEV prototype construction began – all

Tasks to be completed for the upcoming week

  • Design 3D parts – all
  • R&D presentation – all

Decisions made by group (were they a consensus or did the project manager decide?)

The prototype was made with everyone. What the progress report states was decided by consensus.