April

4/01/19

  • HI 308 10:20-11:15AM
  • All members present
  • Worked on AR&D 3 and PR3

4/03/19

  • HI 308 10:20-11:15AM
  • All members present
  • Direct drive experimentation

4/04/19

  • HI 224 11:10-12:30PM
  • All members Present
  • Direct Drive Experimentation

4/08/19

  • HI 308 10:20-11:15AM
  • All members present
  • Perfect FPT Code

4/10/19

  • HI 308 10:20-11:15AM, HI 224 6:20-7:40PM
  • All members present
  • Obtain working AEV components and perfect FPT Code

4/11/19

  • HI 224 11:10-12:30PM
  • All members present
  • Complete FPT

4/15/19

  • HI 308 10:20-11:15AM
  • All members present
  • Work on Final Project documentation

4/17/19

  • HI 308 6:30-8:30PM
  • Ryley, Steve, Conner Present
  • Project documentation