1-24-18

Meeting 3

Date: Wednesday, January 24th, 2017

Time: 3:55-5:15

Location: Hitchcock, 224

Attendees: Joe Malinak, Jordan Thrash, Nick Study, Tyler Szekely

 

Topics Discussed: Our sketched out AEV designs were the main topic.  It was decided that it would be best to have the battery on the bottom because it was the heaviest and only had one wire that needed to be attached.  A basic AEV was constructed off of this model, including propellers and sensors attached.  This week, lab 2 was completed, with the sensors attached fully and tested.  Pictures were taken of the sensors attach for website deliverables.

– Joe, Tyler, and Nick worked on constructing the AEV

– Jordan provided the AEV design that was the most popular with the battery on the bottom

-Jordan and Nick worked on code for testing sensors

 

Upcoming tasks:  Update meeting notes

Catch up on website deliverables

upload pictures of AEV sketches

upload pictures of sensors attached