Lab 7 Schedule & Team Meeting Notes

Note: Lab 6 and Lab 7 fell on the same day. Thus the team meeting notes were the same.

The team met together around 10 AM on Tuesday, February 21. The main discussion was related to which AEV design should be used from the various individual designs thought up in the previous lab. In the end, the group concluded that the bottle design was the first design it would test.
In addition, the group talked about current work related to the AEV. The roles for the next progress report were assigned, and there was discussion about the bonus video and online portfolio. Group member Travis suggested the team work together on the bonus video the weekend before the first part is due. In addition, the team leader, Joseph Dandrea, mentioned that he had written several blogs for the portfolio in Wordpad and would transfer them to the group website within the next couple weeks.

 

Weekly Schedule

Task Teammate(s) Start Date Due Date Time Needed (h)
Progress Report 4 All 2/16/17 2/23/17 2 each
Portfolio Joseph 1/24/17 3/30/17 36
Arduino Storage Davin 2/16/17 2/23/17 168
Bonus Video All 1/26/17 3/2/17 40 total

Leave a Reply

Your email address will not be published. Required fields are marked *