Schedule from 2/9 to 2/16


Date Time Location Team Members Goal
2/7/17 7-9 PM SEL All Brainstorm and decide on AEV body design
2/8/17 6-7 PM SEL All Decide and sketch concept design for Progress Report
2/8/17 7-10 PM Word Doc from Home All Complete Progress Report for Lab 4
2/9/17 2-4 PM Hitchcock Ashwin and Daniel Finetunethe code, have the AEV stop at the gate
2/9/17 2-4 PM Hitchcock Alex and Blake Adjust the AEV to match the concept design
2/14/17 7-10 PM Word Doc from Home All Complete Progress Report for Lab 5