AEV Body Reworking

Time: 2:00pm (Face-to-Face)

Members Present: Blake Kanoy and Alex Beutel

Topics Discussed: AEV Body Design

Objective:

The main focus of the meeting was to adjust and rework the AEV body design to match the concept design that was decided upon in the team meeting on 2/817.

To do/ Action Items:

-Partially deconstruct the original AEV body

-Assemble the decided upon final design

-Inspect the new body and ensure that it matches the design

-Test the new body

Decisions:

-The group decided on the final body design of the AEV

-The group began dismantling and assembling the new body

Reflections:

-The deconstruction took longer than expected due to limitations with tools

-Only having one screwdriver and one crescent wrench limits the ability of the group to work at the same time

-Construction of the new body took longer than expected

-Team did not have time to test the new body and will have to at a later date