Requirement and Test Plan

System Requirement & Score Cards

System Requirements Vehicle Reqs Score Rubric Score
Average Time to Recharge Vehicle <=40min -3% for each more min 17
Load >=2 Trash Bag 50% for each bag 12
Stopping Precision <=6inch 0%/100% 14
Average Time for Vehicles to travel to T-cans <=15min -5% for each more min 16
Price for each vehicle <=$500 -10% for each more $100 6
The average usage time for each vehicle after recharge >=4h -10% for each less 10 min 14
The service life period of each vehicle >=5years – 25% for each less year 11
Number of People to Maintain <=3people -20% for each more person 10

Detail about Systems requirements and Score Card.

Project Management

Research/Progression Days Research Question/Objective Pointer Person
Project 19 (Mon. 11/4) (55 min) Prototype – Does our current design need adjustments? Malik Hollis
Group Meeting (Wed. 11/6) (1.5 hrs+) Prototype – Implement adjustments/upgrades to start testing Xinyun Huo
Project 20 (Fri. 11/8) (55 min) Coding- Can we calculate stopping precision and apply it in code? Yukun Zheng
Project 21 (Mon. 11/11) (55 min) Coding – Can we simulate “speed zones” effectively on track? Gage Odom
Group Meeting (Wed. 11/13) (1.5 hrs+) Prototype – Test current code on track to see what needs adjusted Malik Hollis
Project 22 (Fri. 11/15) (55 min) Coding – Can we move, load, and then return to original position? Gage Odom
Project 23 (Mon. 11/18) (55 min) Coding – Code for two trips of cargo both returning to original position. Yukun Zheng
Group Meeting (Wed. 11/20) (1.5 hrs+) Prototype – Gather data for all predicted stopping points and load points. Xinyun Huo
Project 24 (Fri. 11/22) (55 min) System – Test whole system to make sure everything is working smoothly. Gage Odom