Lab 10 was used to continue the process of trial and error to perfect the code. The team worked on consistently getting the AEV to stop at the exact same location every single run. The vehicle had to be programmed to stop before every gate at the correct point that would trigger the gate open. If the code was even a few marks off, the AEV would not trigger the gate and the run would be unsuccessful. This was a primary concern of the group in this lab.
Weekly Schedule
Task | Teammate(s) | Start Date | Due Date | Time Needed |
Lab 10 Progress Report | All | 3/23/17 | 3/30/17 | 3 Hours |
Lab 10A | All | 3/30/17 | 3/30/17 | 55 Mins |
Lab 10B | All | 4/4/17 | 4/4/17 | 55 Mins |
Lab 10C | All | 4/5/17 | 4/5/17 | 1 Hour 20 Mins |
Update Portfolio | Adam | 3/23/17 | 3/30/17 | 30 Mins |
No Team Meeting this week