March

Team Meeting Notes
Date: 3/4/2017
Time: 1:50-3:00 PM
Members Present: Josh Anson, Jesse Noble, & Bret Ricklic (Nate was gone for break.)

 

Objective:

 

The main focus of today’s meeting was to divide up the work for progress report 9 and PDR.  Afterwards we discussed the PDR and the creating models of AEV in solidworks.
To Do/Action Items:
–         “Backwards Looking Summary” (Situation, Results, Analysis)- Nate
–         “Forwards Looking Summary” (Situation, Weekly Goals)- Bret
–         “Appendix” (Team Meeting Notes, Arduino Code, Matrices, Weekly Schedule)-Jesse
–         “Formatting and Submission, Report Questions, and Take-Aways” -Josh
Decisions:
–         Team H split up both PDR and Lab 9 in order to work ahead

 

Reflections:
–         Team H feels the work coming back from break will be hard but after planning it out it will be easier to maintain.

Take Aways

  • Code to get to gate and stop
  • Working in solidworks to model Team H’s AEV
  • Design testing approach (what to look for in tests)

Meeting 3/30/17:

Members: All

Time / Place:  5:30 Smith Steeb

Items Discussed:  Broken Propeller, Bret’s plan for servo motor, new propeller coming in, troubleshooting difficulties from previous week.

Action Items:  Split up this progress report, tried to fit new propellers onto motors