Meeting #1 (Lab 1)
Date: 20-Jan-2016
Time: 4:00 pm(Face-to-Face)
Members Present: Aisha Iftikhar(AI), Chen Ling(CL), Zhen Tian(ZT), Zihan Zhang(ZZ)
Topics Discussed: Group Final Conceptional Design For AEV
Objective:
The group members need to finish their own designs before coming to the meeting, and the group would choose the best one and make some improvements.
To do/Action Items:
- Final Conceptional Design (AI, CL, ZT, ZZ)
- Outline for Executive Summary(AI, CL, ZT, ZZ)
Decisions:
The group chose part of CL and ZT’s design.
Reflections:
- It is hard to decide which design is better. Perhaps we need some experiments to determine the performance of each design.
- It is not convenient for all members to get together to talk something. Next time we prefer to use online chatting.
Meeting #2 (Lab 1)
Date: 22-Jan-2016
Time: 5:00 pm(Online)
Members Present: Chen Ling(CL), Zhen Tian(ZT), Zihan Zhang(ZZ)
Topics Discussed: The Task Distribution Of Lab 1 Executive Summary
Objective:
The group need to determine each member to finish which part of the summary.
To do/Action Items:
- Outline for Executive Summary(AI, CL, ZT, ZZ)
Decisions:
ZT – Purpose & Background
AI – Observations / Analysis
CL – Scenario Recommendations
ZZ – Conclusions
Reflections:
- Online discussion is convenient and high efficient.
- The task distribution is reasonable.
Meeting #3 (Lab 2)
Date: 29-Jan-2016
Time: 3:00 – 4:00 pm(Face-to-face)
Members Present: Aisha Iftikhar(AI), Chen Ling(CL), Zhen Tian(ZT)
Topics Discussed: The Task Distribution Of Lab 2 Executive Summary and installment of vehicle
Objective:
The group need to determine each member to finish which part of the summary and distribute assembling task of the vehicle.
To do/Action Items:
- Outline for Executive Summary(AI, CL, ZT, ZZ)
- Vehicle installment(ZT)
Decisions:
- Executive Summary
- ZT – Scenario Recommendations & Conclusion
- AI – Purpose & Background & Outline
- CL – Polishing
- ZZ – Polishing
- Vehicle Installment
- ZT – The overall installment
Reflections:
- This discussion is efficient and the team decided to remove the streamline head due to its cost.
Next