Schedule of Semester

There were a lot of assignments due throughout the semester, and in order to keep track of all the assignments, the students have created a schedule with start dates and end dates. There is also a break down of the tasks for who did what.

Task Start Date End Date Completed
Lab 1- Creative Design Executive Summary January 14th, 2015 January 21st, 2015 yes
Lab 2- Arduino Programming Basics Executive Summary January 21st, 2015 January 28th, 2015 yes
Lab 3- AEV Designs Concept Screening and Scoring Executive Summary January 28th, 2015 February 4th, 2015 yes
Lab 4- External Sensors Executive Summary February 4th, 2015 February 11th, 2015 yes
Lab 5- System Analysis 1 Executive Summary February 11th, 2015 February 18th, 2015 yes
Lab 6- System Analysis 2 Executive Summary February 18th, 2015 February 25th, 2015 yes
Lab 7- System Analysis 3 Executive Summary February 25th, 2015 March 4th, 2015 yes
Lab 8- Design Analysis Tool Executive Summary March 4th, 2015 March 11th, 2015 yes
Write PT1 TRR Executive Summary March 9th, 2015 March 11th, 2015 yes
Design AEV Concepts March 10th, 2015 March 11th, 2015 yes
Test Concepts and Extract Data from AEVs March 10th, 2015 March 24th, 2015 yes
Analyze Data March 23rd, 2015 March 25th, 2015 yes
Write PDR March 24th, 2015 March 26th, 2015 yes
Write PT2 TRR Executive Summary March 23rd, 2015 March 25th, 2015 yes
Write PT2 Memo March 28th, 2015 April 6th, 2015 yes
Write PT3 TRR Executive Summary March 29th, 2015 April 2nd, 2015 yes
Make Poster Rough Draft April 2nd, 2015 April 9th, 2015 yes
Write PT3 Memo April 8th, 2015 April 13th, 2015 yes
Finalize Poster April 10th, 2015 April 13th, 2015 yes
Write CDR April 15th, 2015 April 20th, 2015 yes
Update Webpage March 10th, 2015 April 20th, 2015 yes
AEV Showcase April 20th, 2015 April 20th, 2015 yes

 

Tasks Completed (Over Entire Semester)

  • Designing and Modeling AEV Concepts
    • Estimated Time- 4 hours
    • Sean, Logan, Laura, and Matt create initial AEV design sketches
    • Logan and Sean design AEVs
    • Sean designed parts on SolidWorks for 3D-printing
    • Sean builds the designs during the labs
    • Sean and Logan compose SolidWorks models for AEV designs
    • 100% completed
  • Test Concepts
    • Estimated Time- 15 hours
    • Logan and Matt test the AEVs during lab sessions
    • 100% completed
  • Extract Data from AEVs
    • Estimated Time- 45 minutes
    • Logan gets the AEV data and sends the data to Laura
    • 100% completed
  • Analyze Data
    • Estimated Time- 3 hours
    • Laura analyzes the data in Matlab and Excel
    • Sean creates breakdown of AEV data with AEV code
    • 100% completed
  • Update Webpage
    • Estimated Time- 10 hours
    • Laura updates the u.osu.edu page with labs and other documents
    • 100% completed
  • Write Reports
    • Estimated Time- 60 hours
    • Logan, Sean, Matt, and Laura all work together to write reports
    • 100% completed

Leave a Reply