C. Project Schedule

The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done.  This document will be updated throughout the course of the project.

Task Start

Date

Finish

Date

Due

Date

Primary

Person

Secondary

Person

 Est.

Hrs

%

Done

Create u.osu.edu Account

 

10/31 10/31 10/31 Carrington N/A 5 min 100%
User Interview #1

 

10/31 10/31 10/31 Brandon N/A 5 min 100%
User Interview #2

 

11/14 11/14 11/14 Noah N/A 5 min 100%
Flowchart, Algorithm, or Pseudo code Draft

 

11/6 11/6 11/7 Salina Brandon 10 min 100%
Individual Responsibility Agreement

 

11/6 11/6 11/7 Carrington N/A 10 min 100%
Team Working Agreement

 

11/6 11/7 11/7 Noah N/A 30 min 100%
Create Game #1

 

10/31 11/20 11/21 Salina Brandon 15 hrs 100%
Create Game #2

 

10/31 11/20 11/21 Carrington N/A 10 hrs 100%
Create Game #3

 

10/31 11/20 11/21 Noah N/A 5 hrs 100%
PowerPoint Draft

 

11/12 11/14 11/14 Salina Noah 1 hr 100%
Final Software Design Project Plan

 

11/18 11/20 11/21 Brandon Carrington 30 min 100%
Electronic/Print Advertisements

 

11/20 11/21 11/21 Salina N/A 30 min 100%
Demonstration and Final Testing

 

11/21 11/21 11/21 Whole Team N/A 30 min 100%
Software Documentation – Discussion

 

12/1 12/4 12/4 Brandon N/A 45 min 100%
Software Documentation – Final Program with Comments

 

12/1 12/4 12/4 Noah N/A 10 min 100%
Software Documentation – Program Description for Developers

 

12/1 12/4 12/4 Carrington N/A 45 min 100%
Software Design Project Video

 

12/1 12/4 12/4 Whole Team N/A 1 hr 100%