C. Project Schedule

The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done.  This document will be updated throughout the course of the project.

Task Start

Date

Finish

Date

Due

Date

Primary

Person

Secondary

Person

 Est.

Hrs

%

Done

Have a game picked

 

10/31 11/2 11/2 Seth Jonathan 1 100
Flow chart

 

11/2 11/9 11/9 Sam Seth 1 100
Outline

 

11/9 11/16 11/16 Sam Jonathan 1 100
Intro to graphics

 

11/2 11/9 11/9 Sam Jonathan 2 100
Create setup code

 

11/9 11/16 11/16 Seth Jonathan 3 100
Implement graphics

 

11/16 11/21 11/21 Sam Seth 2 100
Code Base game without the CPU

 

11/21 11/21 11/21 Jonathan Seth 3 100
Code CPU logic

 

11/16 11/28 11/28 Seth Jonathan 5 100
Finish Title Screen

 

11/16 11/28 11/28 Sam Seth 3 100
Finalize

 

11/28 11/28 11/28 Sam Seth 2 100
Finish game

 

11/28 11/30 11/30 Jonathan Sam 1 100