Project Schedules
*Schedules for weeks 6,7, and 9 are not present due to progress reports not being required, instead the Lab Proficiency Quiz, Preliminary Design Review Presentation, and Preliminary Design Report were the aspects of the project covered during these weeks*
Table 1: Week 1 Schedule
Task | Teammates | Start Date | Due Date | Time Needed |
AEV Assembly |
All | 1/24/17 | 1/26/17 | 1-2hrs |
Progress Report 1 |
All | 1/26/17 | 2/2/17 | 4hrs |
Table 2: Week 2 Schedule
Task | Teammates | Start Date | Due Date | Time Needed |
AEV Re-assembly |
All | 1/24/17 | 1/26/17 | 1-2hrs |
Progress Report 2 |
All | 1/26/17 | 2/2/17 | 4hrs |
Table 3: Week 3 Schedule
Task | Teammates | Start Date | Due Date | Time Needed |
AEV Drawings | All | 2/3/17 | 2/9/17 | 1-2hrs |
Progress Report 3 |
All | 2/6/17 | 2/9/17 | 4hrs |
Table 4: Week 4 Schedule
Task | Teammate(s) | Start Date | Due Date | Time Needed |
Lab 5 Progress Report | All | 2/9/16 | 2/16/17 | 4hrs |
Portfolio Update | Andy | 2/9/16 | 2/16/17 | 1hrs |
Bonus Video Part 1 | All | 2/16/17 | 3/2/17 | 1hrs |
AEV Modifications | All | 2/9/16 | 2/16/17 | 1hrs |
Table 5: Week 5 Schedule
Task | Teammates | Start Date | Due Date | Time Needed |
Select 3-D Part | All | 2/21/17 | 2/2/17 | 1-2hrs |
Progress Report 6 |
All | 2/21/17 | 2/23/17 | 4hrs |
Table 6: Week 8 Schedule
Task | Teammates | Start Date | Due Date | Time Needed |
Final Design of 3-D Printed Parts | All | 3/7/17 | 3/9/17 | 30 min |
Lab 7 Progress Report | All | 3/7/17 | 3/9/17 | 4hrs |
Begin PDR Report | All | 3/8/17 | 3/23/17 | 4-6hrs |
Table 7: Week 11 Schedule
Task | Teammates | Start Date | Due Date | Time Needed |
Test New Design | All | 4/3/17 | 4/6/17 | 30 min |
Lab 10 Progress Report | All | 4/3/17 | 4/10/17 | 4hrs |
Improve AEV Return Code | All | 4/3/17 | 4/17/17 | 45 min |
Add Battery Mount | All | 4/3/17 | 4/6/17 | 20 min |
Table 8: Week 12 Schedule
Task | Teammates | Start Date | Due Date | Time Needed |
Improve AEV code for
efficient energy use |
Andy and Grant | 4/7/17 | 4/6/17 | 30 min |
Lab 11 Progress Report | All | 4/7/17 | 4/10/17 | 3hrs |
Improve AEV Return Code | All | 4/6/17 | 4/15/17 | 45 min |
Bonus Video | All | 4/10/17 | 4/20/17 | 4hrs |
Start CDR | All | 4/10/17 | 4/20/17 | 10+ hrs |