01/09/19
4:00 PM
Hitchcock 224
Present Members: All (Mulan Blum, Grace DeGidio , Conor Forrestal , Greg Peterson)
Introductions of members of Group C. Start the preliminary research and development for AEV project.
Tasks:
- P R&D Exercise 1 – All
- Website Update 1 – Mulan and Conor (Completed and submitted to Carmen)
Upcoming Tasks
- P R&D Exercise 2 – All
- Website Update 2 – Any Member
- Establish roles – All
- Create approach to MCR
- Determine Timeline – All
01/15/2019
3:00 p.m.
Hitchcock 224
Present Members: All (Mulan Blum, Grace DeGidio, Conor Forrestal, Greg Peterson)
Tasks:
- Website Update 1 – All Members
- MCR Approach – All
Upcoming Tasks:
- P R&D Exercise 2 – All members
- Website Update 2 – Any
- Determine Project Timeline – All members
01/16/2019
3:00 p.m.
Hitchcock 224
Present Members: All
Tasks:
- P R&D Exercise 2
01/23/2019
3:00pm
Hitchcock 224
Present Members : All
Tasks
- AEV Construction
Upcoming Tasks
- Create AEV Individual Designs
- Website Update
- Create Project Timeline
02/06/2019
3:55pm
Hitchcock 308
Present Members: All
Tasks
- Run Efficiency Tests
- Discuss Individual Designs
- Begin Discussions of Group Design
Upcoming Tasks
- Update Website
- Create Final Group Design for AEV
- Progress Report
02/10/2019
2:00pm
18th Ave Library
Present Members: Grace, Mulan, Greg
Tasks
- Work on Progress Report
- Divide Progress Report and Solidworks design into individual tasks
Upcoming Tasks
- Solidworks part presentation
- Committee Meetings
02/27/2019
3:55pm
Hitchcock 224
Present Members: All
Tasks
- Committee Meeting Reflections
Upcoming Tasks
- Test Braking
- Test Voltage
03/01/2019
3:00pm
Hitchcock 308
Present Members: Grace, Mulan, Greg
Tasks
- Test AEV at different voltages
Upcoming tasks
- Test braking
- Performance Test
- Fix up Website
03/05/2019
3:00pm
Hitchcock 224
Present Members: All
Tasks
- Submit design to be printed
- Fix up website
Upcoming Tasks
- Test braking
- Performance Test
03/06/2019
3:55pm
Hitchcock 224
Present Members: All
Tasks
- Test braking
- Begin creating code for the performance test
Upcoming tasks
- Finalize the performance test’s code
- Complete performance test
03/07/2019
3:00pm
Hitchcock 308
Present Members: All
Tasks
- Finalize the performance test code
- Complete the performance test
Upcoming Tasks
- Website Update
- Progress Report
- Presentation