The following is a project schedule including every task, the start and end date and due date, the primary and secondary team member responsible for the task, the estimated hours and the % done. This document will be updated throughout the course of the project.
Task | Start
Date |
Finish
Date |
Due
Date |
Primary
Person |
Secondary
Person |
Est.
Hrs |
%
Done |
Rough blackjack code
|
11/3/18 | 11/3/18 | N/A | Jared Hohman & Aayush Shah | N/A | 4-5 hours | 90% |
Blackjack flowchart | 11/6/18 | 11/6/18 | 11/8/18 | Jared Hohman | Aayush Shah | 2 hours | 90% |
Mastermind algorithm | 11/6/18 | 11/6/18 | 11/8/18 | Paul Crock | Chuqi Zhang | 0.5 hours | 50% |
Rough blackjack code | 11/10/18 | 11/10/18 | N/A | Jared Hohman & Aayush Shah | N/A | 2 hrs | 100% |
Blackjack details + extras | 11/17/18 | 11/24/18 | N/A | Jared Hohman & Aayush Shah | N/A | 2 hrs | 100% |
Video | 11/31/18 | 12/2/18 | 12/2/18 | Jared Hohman & Aayush Shah | Paul Crock | 8 hrs | 100% |
Mastermind finished | 11/10/18 | 11/28/18 | N/A | Paul Crock | N/A | 6 hrs | 100% |
Further Documentation | 11/6/18 | 12/2/18 | 12/3/18 | Jared, Paul, Aayush, Chuqi | N/A | 6 hrs | 100% |